What We Do — Process

  1. Initial coordination — you provide the bank specification (cell count, capacity, technology, age, location). If unknown, we begin with a preliminary site visit.
  2. Site survey and instrumentation — thermal imaging, cell voltage measurement, electrolyte level (where relevant), ambient temperature recording.
  3. Actual capacity test (Cn) — load-bank discharge test at the discharge current and rate specified in the manufacturer's datasheet (e.g. 10, 20 or 100-hour rate). The Ah delivered during discharge is the actual battery capacity — not the nominal.
  4. Internal resistance (Ri) measurement — for every cell or block separately; Ri is a condition indicator (rising Ri is an early aging signal), but it does not replace the capacity test.
  5. Written report and replacement plan — battery-level capacity, per-cell measurement data, risk classification, scheduled cell or full bank replacement recommendation with timeline.

Scope — Structured List

  • Capacity test (Cn) — load-bank discharge at the manufacturer's datasheet rate (e.g. 10, 20 or 100-hour); test duration depends on the rate and the permitted depth of discharge
  • Internal resistance (Ri) measurement — at cell or block level, compared to manufacturer references, as a condition indicator
  • Cell voltage measurement — float voltage, charge voltage, voltage under discharge
  • Thermal imaging — cell surface temperature unevenness (overheating cell, connection fault indication)
  • Technology-specific checks — for OPzS (vented, flooded) cells, electrolyte level and specific gravity measurement; for OPzV, AGM and GEL (valve-regulated, VRLA), safety valve inspection — sealed cells are never topped up with water
  • Weak cell / block replacement — identifying the limiting cells and (where justified) replacing them individually instead of the full bank
  • Replacement planning / replacement schedule — scheduled, cost-efficient strategy, not reactive
  • Written report — battery-level capacity, per-cell measurement data, trend, recommended actions, estimated remaining life

Battery Technology-Specific Maintenance Differences

Every technology has a different maintenance protocol — there is no universal battery service. The manufacturer's design life is a design value at 20 °C, not a guaranteed service life; above 20 °C the expected life decreases, so we plan replacement based on measured capacity.

  • AGM (Absorbent Glass Mat) — valve-regulated (VRLA), sealed block: no water top-up required, but capacity testing is equally necessary. FIAMM AGM blocks have a design life of 10–12 years or more than 12 years depending on the type; in UPS duty at higher temperatures the actual life can be shorter. Ri growth is the main aging signal.
  • GEL — valve-regulated (VRLA), sealed gel-electrolyte design, typically with better cyclic tolerance. Temperature-sensitive — thermal assessment is particularly important.
  • OPzV (valve-regulated, gel electrolyte, tubular plate cell) — widely used in 220 VDC and telecom applications. FIAMM SMG design life: 20 years (20 °C). Maintenance: regular voltage and Ri measurement, safety valve inspection, periodic capacity test per the manufacturer's instructions.
  • OPzS (vented, flooded electrolyte, tubular plate cell — not VRLA) — FIAMM LM design life: 20 years (20 °C). Maintenance: electrolyte level and specific gravity measurement, topping up with distilled (deionized) water per the manufacturer's instructions (acid is never added), ventilation check (EN IEC 62485-2), periodic capacity test.
  • LiFePO4 (lithium iron phosphate) — different parameter assessment: BMS data readout, cell balancing check, cycle counter readout. Manufacturers specify cycle life under stated conditions (e.g. Pytes E-BOX 48100R: 6,000 cycles at 0.5C, 25 °C, 90% DoD; TAB e.motive: 2,000 cycles at 0.5C, 80% DoD); a BMS failure can take down the entire bank.

What Is NOT Included

When You Need It — Triggers

  • Battery 4+ years old (UPS batteries); for older OPzV / OPzS and LiFePO4 banks depending on operating conditions and manufacturer instructions
  • Elevated internal resistance signaled by the supervision system
  • Temperature difference between cells — more than 5 °C at different points of the bank
  • Before UPS or DC system replacement — checking remaining capacity (whether the existing bank can continue with the new system)
  • As a new operator taking over an unfamiliar system
  • Audit / due diligence
  • Post-event check — after an outage where the bank carried the load

What Is the Risk If It Doesn't Happen

The gap between nominal and actual capacity grows with no visible signal. The actual capacity of aging banks can be significantly below nominal while the supervision system still shows the nominal autonomy. This gap has two consequences:

  1. The designed backup time is not delivered — a UPS sized for 15 minutes of backup can in reality carry the critical load for a much shorter time. This gap reveals itself when it is too late.
  2. Replacement planning becomes reactive — after an unexpected failure, procuring a new bank can take weeks, and until then the critical load runs without battery backup.

With regular capacity testing — more frequent for critical systems — replacement planning becomes proactive: within a planned window, with cost-optimized procurement, with a bridging mobile UPS where required.

What the Capacity Test Reports

  • Actual battery capacity (Ah and % of nominal) — the result of the load-bank discharge
  • Per-cell voltage record during discharge — with the limiting (weakest) cells that determine the battery capacity marked
  • Internal resistance at cell or block level (Ri) — relative to manufacturer reference
  • Estimated remaining life — based on capacity trend and manufacturer data
  • Risk classification — critical / medium / low, with replacement priority
  • Scheduled replacement plan recommendation — timeline, estimated cost, procurement window

Pricing Factors

  • Cell count and bank configuration — 24 V, 48 V, 220 V, multiple parallel strings
  • Technology — OPzS also requires electrolyte measurement; LiFePO4 requires BMS data readout
  • Location — Budapest, elsewhere in Hungary, or another country in the Central and Eastern European (CEE) region
  • Accessibility — load bank delivery, downtime window
  • Measurement depth — quick Ri measurement vs. full Cn capacity test with load bank

The duration of a full capacity test is set by the chosen discharge rate (a 10-hour discharge alone takes longer than one working day), plus preparation and recharge; labor and price are given in the individual quotation based on bank size and location.

SLA / Response Time

Capacity testing is planned work — so it is not response time but scheduling that matters. For SLA-contracted partners, capacity testing is part of the planned preventive maintenance schedule. Without an SLA, for an individual order, we agree on the date when the order is placed.