Energom Electronic Kft. designs and installs 220 VDC, 48 VDC and 72/110 VDC power systems for substations, base stations and rail signaling, drawing on 25+ years of experience. Powering these is not a generic UPS task: it requires standards-based topologies, redundant DC architecture and industry-specific expertise — a specialist segment where failure is not an option.

Request a Callback

Typical challenges and how we approach them

The DC supply market is narrow: customers are technical specialists, equipment is engineered, and standards are strict. Three recurring situations bring us into projects in Hungary.

1. 220 VDC supply for substation protection systems

Challenge: Medium- and high-voltage substation protection and control systems (relays, breakers, regulators) are powered from 220 VDC. A power outage or DC supply loss can disable the protection function — fault detection and isolation can be delayed, potentially leading to a wider outage. The requirement is not „adequate operation" but operation at the worst possible moment.

Solution: We design redundant 220 VDC systems — dual-feed input, monoblock or modular rectifier, lead-acid (OPzV/OPzS) or LiFePO4 battery bank. The system is sized by Cn (10/20/100-hour rate); the multi-hour autonomy is set by the operator's specification and the site's accessibility. Inverter modules supply low-power 230 VAC control devices. We work alongside designers operating in regulated grid environments to deliver the system design package.

2. 48 VDC supply for telecom base stations

Challenge: A telecom base station or core switching room operates on 48 VDC supply — the industry standard. An outage can mean coverage loss, unavailable emergency calls and regulatory consequences. Sites are often small with limited cooling — thermal load and remote supervision are critical.

Solution: We deploy modular 48 VDC power systems with hot-swap rectifiers and integrated battery monitoring (AGM or LiFePO4). Modules are configured in N+1 redundancy, typically 6-30 kW per site. Remote supervision via SNMP — voltage, current, temperature and battery state trends are visible without site visits. For new installations, cabling is designed in continuity with the existing -48 V infrastructure. With regular maintenance and measurement-based battery replacement, the system can be kept close to the manufacturer's design life.

3. 72/110 VDC supply for rail signaling and station infrastructure

Challenge: Rail signaling, interlocking and station communication systems operate on 72 VDC or 110 VDC supply. Rail operations do not tolerate unplanned outages — operational safety, infrastructure manager regulations and strict EMC requirements (EN 50121) constrain the designer. Environmental demands (temperature range, vibration, IP rating) are stricter than the industrial average.

Solution: We design and install 72/110 VDC power systems suitable for rail applications — built to EN 50121-4 (EMC of signaling and telecommunication apparatus) as the project requires; environmental tolerance is defined by the selected product's datasheet. Battery banks are typically pure lead or LiFePO4 due to long cycle life. A redundant DC bus with parallel rectifier modules keeps the supply available even during maintenance. Installation planning includes track-side work windows and safety regulations.

Recommended product categories

A DC solution is not one box but a system: rectifier, battery bank, distribution and monitoring designed together.

220 VDC systems — Power plants, water and gas utilities, rail auxiliary supply. From 100 W to several hundred kW, monoblock and modular.

48 VDC systems — Telecom and communications applications. Hot-swap modular design with remote supervision.

72/110 VDC systems — Power for rail and industrial switchgear.

Industrial batteries — OPzV, OPzS, pure lead, LiFePO4 — the autonomy basis of the DC system.

Energy management systems — DC bus monitoring, battery state supervision, alarm integration with SCADA.

Related services

After design and installation, maintenance and monitoring deliver the actual availability of the DC system.

Site survey and design — On-site survey, standards-based system design, documentation package.

Turnkey installation and commissioning — Installation, cabling, commissioning, Site Acceptance Test (SAT).

Maintenance and service — Scheduled preventive maintenance, rectifier health checks.

Battery maintenance — Internal resistance measurement, load-based capacity testing, replacement planning.

Monitoring and optimization — SNMP-based remote supervision, alarm forwarding, predictive maintenance.

Who we work with

DC solutions are industry-specific — standards, environmental demands and redundancy levels all reflect the application area.

Power plants — 220 VDC supply for protection and control, plus the auxiliary supply needed for black start.

Utilities (electricity, water, gas) — Substations, pump houses, gas receiving stations and their protection systems.

Railways — Signaling, interlocking and communication systems at rail and industrial-rail sites.

Telecommunications — Base stations, core switching, optical nodes powered by 48 VDC.

Industrial switchgear — High-voltage switchrooms, industrial transformer protection systems.

Data center auxiliary DC — Where dedicated 48 VDC or 220 VDC segments are needed alongside UPS.

Industries we serve →

DC Power Systems — Frequently Asked Questions

The most common engineering questions related to the DC power systems solution page — covering 48 VDC telecom, 220 VDC power plant and substation, and 72/110 VDC railway applications.

What is the role of 220 VDC at substations?

A 220 VDC system at substations provides auxiliary power for protection and control circuits, circuit-breaker operating coils, indicator lamps, and communication and SCADA equipment. The system keeps operating when AC mains is lost — substation protection and switching functions are most critical at exactly the moment the grid sees a disturbance.

It is an established voltage level in Hungarian and European generation and transmission infrastructure. The typical configuration: redundant charger-rectifiers, a battery bank (usually OPzS or OPzV), a DC distribution panel and a supervision system (often IEC 61850-based).

For reliability, a redundant rectifier configuration and measurement-based battery replacement planning are recommended. 220 VDC systems →

What is the difference between a 220 VDC power plant system and an industrial UPS?

The main function of a 220 VDC system is not uninterruptible AC power but a direct DC bus for protection and control circuits (relays, breakers, controls). An industrial UPS provides AC output for sensitive AC loads. A 220 VDC system is designed for multi-hour autonomy — the exact value is set by the operator's specification and the site's accessibility. Battery banks are sized by Cn (10/20/100-hour capacity), not kVA. At many sites the UPS and the DC system operate side by side, complementing each other.

Why is 48 VDC the telecom standard — why not AC?

48 V DC supply (nominally -48 V) is the established telecom standard (in Europe, described in ETSI EN 300 132-2), for historical and technical reasons: the low-voltage DC bus is safe, backup comes directly from the battery bank (no inverter loss), and the battery string is matched to the 48 V nominal voltage. Modern base stations and communication centers are still powered from 48 VDC. AC-powered ancillary equipment (cooling, lighting) is fed from a separate UPS or generator. 48 VDC systems →

How do we engineer a 48 VDC base station power system?

Engineering has three main steps. First, we capture the DC consumption of the critical load (radio units, transmission equipment, climate control, signaling) — typically 600-3,000 W. Second, we set the backup time: for a macro base station typically 4-8 hours (until a generator arrives or mains is restored). Third, we select rectifier redundancy (typically N+1) and battery technology.

Typical configuration: 1U or 2U rack-mounted redundant rectifier modules, a battery bank, a supervision module and DC distribution. The battery build differs by technology: for OPzV, 24 × 2 V cells in series; for LiFePO4, 15 cells in series (48.0 V nominal) or 16 cells (51.2 V nominal), also as a ready-made module; the variant is chosen based on the voltage limits of the rectifier, the loads and the BMS. At high ambient temperature the expected life of every technology shortens (for lead-acid, above 20 °C), and the permitted operating temperature range of LiFePO4 modules is model-dependent — in an outdoor cabinet, climate control is therefore part of the sizing.

Exact engineering is based on load capture and a site survey. Site survey →

What redundancy is required for power plant DC supply?

For power plant and substation 220 VDC supply, redundancy is set by the grid licensee's or operator's specification. For critical protection supply, a dual independent system (2 × 100%) with two separate battery banks and two charger systems is common; in other cases N+1 rectifier redundancy with a single battery bank is accepted. In a dual system the two branches can be operated and maintained independently — while one is out of service for maintenance, the other fully supplies the protection systems.

In a dual system the two branches are typically physically separated in different rooms or cabinet groups, and the distribution panels carry selective protection so that no single short circuit affects both branches. Monitoring is generally connected to the substation SCADA via IEC 61850.

Battery banks are designed for multi-hour autonomy; the exact value comes from the operator's specification and site accessibility. 220 VDC systems →

What is the difference between AGM, OPzV, OPzS and LiFePO4 batteries in DC systems?

The first three are lead-acid technologies, but they differ significantly in life, maintenance and application. The manufacturer's design life is a design value referenced to 20 °C, not a guaranteed service life.

  • AGM: valve-regulated (VRLA) sealed monobloc; no water topping-up, but regular inspection and testing are needed. FIAMM AGM monoblocs have a design life of 10–12 years or more than 12 years, depending on the type. For compact systems (small base stations, indoor cabinets).
  • OPzV: valve-regulated (VRLA), gel electrolyte, tubular plate cell. No water topping-up, but VRLA cells also emit gas, so ventilation must be sized per EN IEC 62485-2. FIAMM SMG design life is 20 years. For macro base stations, substation auxiliary supply and rarely visited sites.
  • OPzS: vented, flooded (liquid electrolyte) tubular plate cell, not VRLA. Requires regular electrolyte level and specific gravity measurement; water lost through gassing is replaced with distilled (deionized) water per the manufacturer's instructions — never acid. FIAMM LM design life is 20 years. For serviceable, critical power plant and large substation environments.
  • LiFePO4 (lithium iron phosphate): lower weight and footprint, manufacturer cycle life stated under defined conditions (e.g. Pytes E-BOX 48100R: 6,000 cycles at 0.5C, 25 °C, 90% DoD), higher capital cost; requires a BMS and compatible charging.

Above 20 °C the expected life of every lead-acid technology shortens, so we plan replacement based on measured capacity. The choice depends on the site, accessibility, ambient temperature and lifecycle cost, based on a sizing calculation. Industrial batteries →

Can we replace an existing lead-acid DC battery bank with LiFePO4?

In many cases, yes. Switching to LiFePO4 can reduce footprint and maintenance burden and increase cycle life; the actual gain depends on operating conditions (discharge profile, temperature), charger settings and BMS integration. The change is not a simple drop-in replacement: charging voltage, charging current, temperature window and communication protocol all differ from lead-acid.

The change typically requires: a compatible battery management system (BMS), a charger-rectifier that can be configured for or supports LiFePO4, appropriate DC protection (LiFePO4 short-circuit behavior differs from lead-acid), and re-engineered placement (fire protection, cooling). In power plant and railway environments, type testing and a manufacturer declaration are also required.

We assess existing system compatibility and the economics of the change in a site survey. Request a quote →

What does EN 50121 mean for rail power supplies?

The EN 50121 standard family covers electromagnetic compatibility (EMC) for railway applications. EN 50121-4 sets the emission and immunity requirements for signaling and telecommunication apparatus. A DC power supply must not only deliver voltage but operate stably under railway disturbances (sudden load changes, harmonics). We select products with the EMC compliance the project specifies and document compliance in the Site Acceptance Test (SAT) report. 72/110 VDC systems →

Can we refurbish an 8-10 year-old DC system?

Yes — modular DC systems are generally well suited to refurbishment. Replacing rectifier modules, renewing the battery bank and updating the control electronics can extend useful life by several years; we quantify the expected life extension and cost after the site survey. A full replacement is justified if the protection system's capacity requirement has grown (new bays, new protections), or if the manufacturer has placed the model into EOL without spare parts support. The recommendation is based on rectifier condition, battery internal resistance and measured capacity, and cable condition. Maintenance and service →

How does DC supply integrate with substation SCADA / IEC 61850?

Modern power plant and substation DC power systems typically connect to the substation SCADA via IEC 61850 — the widely used communication standard for digital substations. Measurement and status data (battery voltage, charging current, temperature, fault indication) are delivered in MMS reports, while fast event signals are sent as GOOSE messages to the substation operator interface.

Where IEC 61850 is not available, integration uses Modbus RTU/TCP, DNP3 or IEC 60870-5-104, and in telecom typically SNMP; protocol support is checked for the specific system selected.

Integration parameters (signal list, alarm hierarchy, event logging) are defined together with the SCADA designer during the engineering phase. Energy management systems →

More Questions?

Continue to the full FAQ → — or get in touch.

If your problem is different

DC systems are a narrow specialization. If your application is more about AC critical loads or bridging longer outages, two of our other solution areas are more relevant.

Uninterruptible Power Supply — When the target is sensitive AC equipment (servers, CNC, medical devices).

Backup Power — When generator-based bridging is needed for longer outages, in hospital or utility environments.

Let's design a standards-based DC system together

Request a quote — our engineers bring industry-specific experience to sizing, redundancy concepts and standards-based system design.

Request a Quote

We respond within 24 hours on business days. +36 1 459 8010 energom@energom.hu